Sorry for the delay, but I was hoping to have pictures before posting again. Unfortunately (or fortunately) people have been working on the house every time we've been by lately, so no good pictures this time.
Anyway, last week on Tuesday we met Brian from Guardian to do the walk through. We met him after work around 5 PM, so it got dark quickly! Basically we just walked through all the rooms with him and pointed out where we wanted the cable and data ports to be placed. There was some confusion about our sound and speaker set up in the basement, but we finally got it sorted out. We have been back by since then and all the wiring for Guardian and the other electrical work has been properly installed! Side note: the windows and exterior doors were also installed when we went!
Monday of this week we did the pre-drywall walk through with our PM. Basically, we just walked through the house, asked questions, and let our PM point out things. So far, all the duct work, electrical and plumbing stuff has been run and the bathtubs are installed. We only noticed one error, they forgot to delete one of the master closet doors, but our PM said that would be a quick and easy fix.
So, on Monday our PM said the plan was to get 3 inspections on Tuesday, do insulation on Wednesday, inspect insulation on Thursday, and start drywall Friday or Saturday. The most recent update today said that they are still waiting on 2 of the 3 inspections they had planned on Tuesday with hopes of accomplishing them today. At this point he thinks the drywall will begin on Monday.
We asked our PM if we're still on track for a December 5th final walk through. He said "we're cutting it close" and he won't be able to really put a firm date on anything until the drywall is done. We are hoping to close by December 12th since as of December 19th we will be homeless when our current house closes!
We will try for pictures this weekend so you can see the windows and hopefully some insulation!
Until next week: